Arrive on site, position drill rig over the site of the proposed bore hole, put down stabilisers and sleepers, secure rig, then raise the mast for commencement of drilling.
Drill down through overburden, insert steel lining and grout between the steel lining and the bedrock and continue to required depth.
Withdraw drilling rods, insert blue well liner, and gravel pack or grout, between the casing and the rock. Lower the mast return stabilisers to road position, and move rig from over the new bore hole.
Cap the well until ready to install submersible pump.
Remove vehicles and equipment from site on completion.