Water Well Drilling Procedure

Water Well Drilling Procedure

Arrive on site, position drill rig over the site of the  proposed bore hole, put down stabilisers and sleepers, secure rig, then raise the mast for commencement of drilling.

Drill down through overburden, insert steel lining and grout between the steel lining and the bedrock and continue to required depth.

Withdraw drilling rods, insert blue well liner, and gravel pack or grout, between the casing and the rock. Lower the mast return stabilisers to road position, and move rig from over the new bore hole.

Cap the well until ready to install submersible pump.

Remove vehicles and equipment from site on completion.

Website design by Zazsi Web Design, Ballincollig , Cork.
Part of Zazsi Digital Media Agency Cork.

Leo O'Sullivan Water Well Drillers Ireland
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

See our Privacy Policy here.